SHC group leaders attend update on renovation works

A section of the attendees listening attentively to the presenter during the update given to group leaders of the Sacred Heart Cathedral Parish at the parish centre, 19 Apr 2018.

KOTA KINABALU – Over 60 group leaders and members of the Sacred Heart Cathedral Parish here attended an update on renovation works and other matters at the parish centre on 19 Apr 2018.

Anthony Lim, chairman of the parish finance council, updated the audience on the renovation works carried out at the parish centre since 2016, using the proceeds from the bazaar that year.

Completed renovation works included electrical rewiring, replacement of faulty main pipe (2016), roofing and gutter system, construction of storage rooms and passageway, repainting, renovated meeting rooms on first floor, and installation of two giant fans in the hall (2017).

In early 2018, overhauling of PA system and video link upgrade between cathedral and hall were done and two LCD screens were installed in the hall.

The other works to be done in 2018 will be the PA system in the meeting rooms and hall as well as the external repainting of the hall.

Lim then appealed to the attendees for cooperation among their members in the use and maintenance of the parish centre facilities such as aircon units and motorised screens (F6, F7, F8), and to observe no-food-drink-rule inside meeting rooms, and other rules.

He also gave a brief update on the progress of the construction of the new Catholic Centre.  He said the earthworks have been completed.  Piling works are scheduled to begin at the end of May until the end of July.  The main building construction will then begin until November 2019.

However, he said, instead of RM1m quota, the quota has been raised to RM2.5m for the cathedral parish.  And that led to the upcoming fundraising bazaar on June 10 in aid of the building fund.

Anita Tunggolou, chairperson of the parish fundraising committee, announced the allocation of bazaar stalls to the different groups, communities, ministries based on the 2016 data.  The target is RM300,000.

In his closing remarks, Archbishop John Wong thanked everyone for their presence, gave a brief background on the decision to build the Catholic Centre, and urged everyone to play their part in the building of this landmark of the archdiocese.

SHC parish group leaders updated on renovation works

Group leaders take their allocation of tickets after the updating and briefing, 5 Oct 2017, SHPC.

KOTA KINABALU – Leaders and representatives of 65 parish groups, ministries, committees and communities of Sacred Heart Cathedral here attended an updating-cum-briefing by their parish priest Archbishop John Wong and his assistants on 5 Oct 2017 at the parish centre.

At the meeting, Anthony Lim, parish finance council chairman, updated those present on the progress made on the major renovation works made at the parish centre last year.

In 2016, two major works were done: re-wiring of the parish centre (RM63,250.00) and replacement of the leaking main pipe (RM31,300.00).  General repair work was also done amounting to RM15,357.69.

Earlier this year, the roofing gutters were repaired (RM21,800.00) as well the complete renovation of the male and female toilets on the first floor (RM85,160.00).

It is hoped that renovation of all the rooms, repainting of walls, repair and replacement of air-conditioner units, replacement of carpets and curtains, building of storage cubicles on both sides of F7, and installing of two units of big ceiling industrial fans in the parish hall will be completed before the end of the year.

After the updating, Abp Wong briefed the attendees on the parish participation in the construction of the RM9.6m Catholic Centre.

He explained the need for it and its location.

The prelate told them that all parishes and subparishes in the archdiocese have been allocated an amount according to their means.

For the cathedral parish, the prelate continued, it is RM1 million.

Anita Tunggolou, head of the parish fundraising committee, informed the leaders that the time frame for fundraisers is one year: August 2017 to August 2018.

The committee has decided on three main fundraisers: a)  third collection on first Sundays (started Sept 2017); b) lucky draw on Dec 31 and c) bazaar in June 2018.

For the lucky draw, all the groups have an allocation of tickets (RM20/booklet) within a period of three months for diffusion.  Contact person is Michelle Linggi, treasurer of the fundraising committee.

Pledge cards for individual donors (Catholics and non-Catholics) are also available at the parish office under Johnny Chong.

The groundbreaking event, Lim said, will be at the end of the year (2017). The construction is scheduled to be completed within two years.

This was the second briefing for the parish group leaders.  The first was held on 2 March 2017.